For UK specialist subcontractors · England & Wales

Never lose track of a construction payment deadline.

NotifiedSum helps specialist subcontractors organise payment dates, track notices and monitor overdue amounts across all their contracts.

Early-stage product from an independent founder. The free calculator works today; the full product is being built with founding customers. No card, no commitment.

Example contract · fictional · calculated by the free tool

Monthly application: 15 Dec 2026

  • Tue 22 DecPayment due date7 days after application
  • Tue 29 DecLast day for the payer's payment notice25 & 28 Dec not counted
  • Fri 15 JanLast day for a pay less notice7 days before final date
  • Fri 22 JanFinal date for payment28 days after due
The problem

Every contract runs its own payment clock. Most firms track it in spreadsheets and inboxes.

Many clocks at once

Each subcontract has its own application date, due date, notice periods and final date for payment. Five live contracts means five clocks every month, each with its own dates.

Deadlines set by law

Under the Construction Act, payment notices and pay less notices have fixed windows. Bank holidays shift the dates. Christmas and Easter are where mistakes happen.

Late notices are common

In a 2026 survey of 127 UK subcontractor professionals, only 46% said they regularly receive payment notices or feedback on time. Source: PBC Today / Payapps report

Late payment costs the UK economy about £11bn a year, according to the UK government. Source: GOV.UK

Why the dates matter

In published disputes, the outcome turned on dates and notices.

These are other companies' disputes, taken from public judgments and law-firm summaries. They are not NotifiedSum customers and the outcomes depended on their own contracts.

£106,434.88

VMA Services v Project One London (2025)

No payment notice or pay less notice was served against a valid application. The adjudicator held the full application sum was due.

Bevan Brittan summary · Judgment

£342,385.52

Gypcraft (2025)

The contractor's payment notice was 5 days late and no pay less notice was served. The subcontractor's claim that its application was the notified sum succeeded.

DWF summary · DAC Beachcroft summary

£867,031.36

Placefirst v CAR Construction (2025)

An adjudicator awarded this sum to the subcontractor over the form of the contractor's notice. The court then looked at the substance of the notice. Exact wording and timing were decisive either way.

Irwin Mitchell summary

Late = nothing

Liberty Roofing v Midleton Developments (2026)

The subcontractor's application and notice were served late, so there was no notified sum. The court refused to enforce the award. Payees miss dates too.

DAC Beachcroft summary

NotifiedSum does not decide whether a notice is valid, and it cannot prevent every loss. It makes sure you know the dates in time to act, or to take advice.

How NotifiedSum works

Enter your contract's periods once. See every date, on every contract.

1

Add a contract

Copy the payment periods from your subcontract (application date, due date, final date, pay less period), or use the Scheme defaults. About five minutes per contract.

2

Get the dates and reminders

Every payment notice, pay less and final date, with bank holidays handled, sent to your calendar plus a Monday email digest.

3

Track what happened

Record notices received and payments made. See overdue amounts, statutory interest and retention release dates across all contracts.

Works alongside what you already use: Excel, Xero, QuickBooks, Sage, and Payapps where your main contractor requires it. NotifiedSum is not an ERP and doesn't replace your accounts.

Product preview

What your Monday view will look like

Illustrative mock-up of the planned product. Fictional companies and figures. The product is in development; the free calculator below is live.

NotifiedSum · Example Drylining Ltd (fictional)Week of 11 Jan 2027
6
Live contracts
4
Deadlines in the next 14 days
£84,250
Applied for, not yet paid
£12,600
Past the final date
Contract (fictional)Next eventDateStatus
School extension · Example Build LtdPay less notice deadline (payer)Fri 15 JanNo payment notice recorded
Warehouse fit-out · Example Construction LtdFinal date for paymentMon 18 JanPayment notice received
Clinic refurbishment · Example Contracts LtdOverdue since 4 Jan£12,600Interest accruing
Your sub: Example Ceilings LtdYour payment notice is dueWed 13 JanYou are the payer
Free tool

Construction payment deadline calculator

Enter your dates and periods. The calculator shows every date and exactly how it was counted.

Which periods apply?
Use the periods written in your subcontract.
If your contract doesn't say, the Construction Act method is the usual starting point.
The Scheme due date is the later of 7 days after this date and the date of your claim.
After the application
After the due date
Days before the final date for payment. Example values shown: replace them with your contract's.

Scheme defaults: final date 17 days after due; pay less notice 7 days before the final date; payment notice 5 days after due.

Stays in your browser. Used only on your printout and calendar file.
Your dates will appear here, with the working shown for each one.
Overdue? Estimate statutory interest

Late Payment of Commercial Debts (Interest) Act 1998: simple interest at 8% above the reference rate, plus fixed compensation. Whether it applies depends on your contract. Use the reference rate that applies to the period (the Bank of England base rate on 31 December or 30 June before it).

Retention: amount held and release dates

Illustration of the common two-half release: one half at practical completion, one at the end of the defects period. Your contract may differ. Retentions are due to be banned under the Commercial Payments Bill after a transition period; existing retentions still need tracking.

Assumptions, sources and limits
  • s.116 counting: a period starts the day after the start date. Christmas Day, Good Friday and England & Wales bank holidays are not counted; weekends are. s.116
  • Payment notice: not later than 5 days after the payment due date. s.110A · payee's notice in default: s.110B
  • Pay less notice: not later than the agreed period before the final date for payment. s.111
  • Scheme defaults: due date = later of 7 days after the relevant period and the claim; final date = due + 17 days; pay less = 7 days before the final date. Scheme, Part II
  • Bank holidays: England & Wales, . GOV.UK list
  • Not covered: Scotland and Northern Ireland; contracts excluded from the Act (e.g. work for a residential occupier); whether your contract terms comply with the Act; whether any notice is valid.

This is an illustrative administrative tool, not legal advice. It does not read or interpret your contract and does not decide whether any application or notice is valid. Always check dates against your contract and take advice where money depends on it.

Pricing

Simple monthly plans. Founding customers lock their price.

Nothing is charged today. Reserve a founding place below; you'll hear first when paid plans open.

Starter

£29 / month

Up to 5 active contracts

  • Every payment date and notice deadline
  • Email reminders and Monday digest
  • Calendar feed (Google, Outlook)
  • Overdue amounts and statutory interest estimates
Founding customers (first 20): your founding price stays locked for as long as you subscribe, plus a 30-day money-back guarantee once paid subscriptions launch. Reservations are free and non-binding.
FAQ

Questions

Is this legal advice?

No. NotifiedSum calculates and organises dates from the periods you enter and shows the working. It does not tell you whether a contract term, application or notice is valid. Take advice from a solicitor or construction consultant where it matters.

Does it read or interpret my contract?

No. You copy the payment periods from your subcontract. That keeps the tool transparent: every date can be traced back to a number you entered.

We already use Payapps, Xero or a spreadsheet. Why add this?

NotifiedSum is not an accounts package or an application builder. It is one view of the deadlines across all contracts, including ones where the main contractor uses a different system, plus the contracts where you are the payer.

Does it cover Scotland or Northern Ireland?

Not yet. The calculator uses England & Wales bank holidays and the England & Wales Scheme.

What does a founding-price reservation mean?

You tell us you'd like a founding place. It is free and non-binding: no card, no contract. When paid plans open, you'll get the founding price offer first and can decide then.

When will the full product launch?

It's being built now, starting with founding customers. Reserving a place helps decide what gets built first.

What happens to the numbers I type into the calculator?

They stay in your browser. We only count that a calculation happened (no cookies, no personal data). See the privacy information.

Who is behind NotifiedSum?

An independent founder. There is no larger company behind it. See below.

About

Built by an independent founder, in the open

NotifiedSum is an early-stage product built by Roberto Ferreri, an independent founder based in the EU. There are no investors, no long company history and no customers yet. The free calculator is the first working piece.

I'm not a solicitor or a quantity surveyor. What I can do is careful, transparent date arithmetic and organisation: every date shows how it was counted, with links to the legislation so you can check it yourself.

If you run a specialist subcontracting business, I'd value one reply: how do you keep track of payment deadlines today?

Founding customers

Reserve a founding place

Free and non-binding. No payment is taken now. The first 20 founding customers keep their price for as long as they subscribe.

  • Starter £29/month or Pro £59/month, locked
  • Direct say in what gets built first
  • 30-day money-back guarantee once paid plans launch

Just want launch news?

Plan you'd reserve

We use these details only to manage your reservation and contact you about it. Privacy information

Contact

Email only, answered within one working day

notifiedsum@gmail.com

No sales calls. Ask anything by email.

Privacy

Privacy in brief

Calculator inputs stay in your browser. We count calculator use without cookies or personal data. Reservation and waitlist details are used only for your reservation and launch news, never sold. If we emailed you, we found your company's address on its own website; you can opt out at any time and we'll never email you again.

Full privacy information